Insider Daily, Stat digital
Romania's digital authority completes a 758 million lei project to move state applications into the government cloud
The MAS IC project, funded through the recovery plan, targeted at least 30 digital service applications made ready for the cloud. The announcement does not say how many were actually moved, or which.

Pe scurt
- The project cost 758.85 million lei, of which 627.15 million came from EU funds
- The target was to migrate at least 30 government applications to the cloud
- ADR has not published the list of applications or beneficiary institutions
The Authority for the Digitalisation of Romania (ADR) announced on 20 November the completion of the "Migration of applications and IT systems to the cloud" project (MAS IC), carried out with the Ministry of Research, Innovation and Digitalisation. The project cost 758.85 million lei, of which 627.15 million lei came from EU funds through the National Recovery and Resilience Plan, and ran from July 2023 to 31 August 2026.
The aim was to make applications used by central institutions cloud ready and move them into a secure private government cloud. The stated target was at least 30 government digital service applications migrated to PaaS or IaaS infrastructure, plus new applications built directly for the cloud.
ADR's announcement says central administration applications were adapted and migrated, but gives neither the exact number of systems nor the institutions whose services were moved. When the financing contract was signed, the project was scheduled to end on 30 June 2026, so it ran two months longer.
MAS IC complements the main recovery plan investment in building the government cloud infrastructure, on which the migrated applications depend.
De ce contează
The government cloud is the infrastructure on which public digital services will run in the coming years. New state applications will be designed for this platform, which matters for the IT companies that will build and maintain them.
Unghiul Insider
For 758 million lei, the public should learn exactly what was moved, for whom and what changed for citizens. Without a list of migrated applications and the indicators achieved, it is hard to say whether the project delivered more than its minimum target.
Surse
- ADR, official announcement, 20 Nov 2026
- ADR, financing contract announcement, 2023
- Go4IT, 21 Nov 2026