600 parking sensors installed in Arad have never been switched on. What any city hall can learn from it
The recovery plan project cost 2.9 million lei. The sensors are wired in series, so they cannot be switched on section by section while the boulevard's pavements are being rebuilt.

Pe scurt
- 600 sensors installed since 2024 in central Arad, on Bulevardul Revoluției
- Cost: 2,888,000 lei including VAT, funded through the recovery plan
- The driver app exists, but the system has not been activated
Arad City Hall announced in autumn 2023 an app that would show drivers free parking spaces in the city centre. In 2024, 600 sensors were installed, mostly on Bulevardul Revoluției. In October 2024, City Hall said the system would be activated in 2025.
According to City Hall's reply published in April 2026, the project was completed but not put into operation. It cost 2,888,000.41 lei including VAT, funded through Romania's recovery plan. The app has been built and, once launched, would show free spaces based on the car's GPS position.
The official explanation is the building site. The pavements on Bulevardul Revoluției are being rebuilt, and the sensors are wired in series, so they cannot be activated segment by segment. City Hall could not give a firm date. Its estimate was that the pavement works would finish in the autumn and the system would be launched afterwards.
The case is not unique. Smart city projects funded with EU money have strict deadlines for procurement and installation, but they are rarely coordinated with infrastructure works in the same area. The result: equipment that has been paid for and installed, waiting for the city to finish something else.
De ce contează
For any city hall or supplier preparing a sensor project, the Arad case shows where money is lost: not in the technology but in coordination with the rest of the city's works and in the system's architecture. A system that cannot start in parts depends on the slowest building site in the area.
Unghiul Insider
The technical lesson is simple and cheap: require in the specifications that the system can be switched on in segments. The management lesson is harder: a smart city project has to be planned together with the investment department, not in parallel. Otherwise the recovery plan pays for sensors sitting under new asphalt.
Surse
- Economedia, răspunsul Primăriei Arad, 20 Apr 2026
- Antena 3 CNN, senzorii de parcare din Arad, 20 Apr 2026