Insider Daily, Smart City
Bucharest is building 122 charging stations in STB depots so that the electric buses bought in 2023 can all run
The investment is 96 million lei. Without chargers in the depots, part of the 100 electric buses could not run at the same time.

Pe scurt
- 122 stations: 55 at Berceni, 52 at Bujoreni and 15 at Bucureștii Noi
- Investment of 96 million lei, according to City Hall
- Works started in June 2026
Bucharest City Hall is setting up 122 charging stations for electric buses in three depots of the Bucharest Transport Company (STB): 55 at Berceni, 52 at Bujoreni and 15 at Bucureștii Noi. The projects were approved by the General Council in May, at the proposal of Mayor General Ciprian Ciucu, and the announced investment is 96 million lei.
The project fixes an old problem. The city bought 100 electric buses in 2023 with EU funds, but they could not all run at the same time because the depots did not have enough chargers. The buses have to charge overnight at their home depot.
Works began in June. In the first phase, the trolleybus overhead lines were removed and the area where the chargers will be fitted was reorganised. Besides the chargers, the project includes rebuilding the parking platforms in the three depots.
City Hall said in May that the money comes from the local budget. News.ro later reported that the project also has an EU funding component and that works must be finished by December.
De ce contează
The 100 electric buses are one of the largest recent investments in Bucharest's public transport. Without charging infrastructure their value is only half used, and operating costs stay high because diesel buses make up the difference.
Unghiul Insider
The story of electric buses that cannot leave the depot is the classic lesson of electrification: the vehicle is the easy part, the grid is the hard part. Any city that buys electric buses before finishing the chargers and grid connections will repeat exactly this scenario.