    Bucharest's smart traffic lights: 92 intersections, 190 million lei and funding that has to be found from scratch

    The General Council approved the first stage of the project in May. The recovery plan money was lost, and City Hall has asked the Bucharest-Ilfov Regional Development Agency for 85 million lei in grants.

    GoTech World Newsroom,

    Bucharest's smart traffic lights: 92 intersections, 190 million lei and funding that has to be found from scratch
    GoTech Insider infographic

    Pe scurt

    • First stage: 92 intersections and pedestrian crossings, 305 cameras and 1,500 sensors
    • Total investment: 190.3 million lei including VAT, or 57.6 million euros
    • Recovery plan contracts worth 73 million lei were lost because works did not start in time

    The Bucharest General Council approved on May 13 the feasibility studies and technical and economic indicators for upgrading the first 92 intersections and pedestrian crossings and the traffic command centre. The total value is 190.3 million lei including VAT, or 57.6 million euros.

    The project has two stages. The first, worth 38.3 million euros, upgrades the traffic lights at the 92 locations with more than 300 video cameras, 1,500 sensors fitted in the asphalt and on poles, new traffic controllers and pedestrian buttons. The second, worth 19.3 million euros, rebuilds the traffic centre on the ground floor of the City Hall building, hardware and software. According to City Hall, the system will give priority to buses and trolleybuses so they reach stops on schedule.

    Funding is the hard part. The project had been tied to recovery plan contracts worth 73 million lei, signed in June and September 2023, on condition that works were finished by July 2026. The works did not start and the money was lost. In June, City Hall submitted a grant application of more than 85 million lei for the first phase to the Bucharest-Ilfov Regional Development Agency. A reply was expected within three months.

    The final target is about 540 intersections, in four stages. The feasibility study was produced by a consortium of Tehno Consulting Solution and Isbak Istanbul IT and Smart City Technologies. The current traffic management system, BTMS, was built in 2007-2009 with an EBRD loan.

    De ce contează

    Smart traffic signalling is one of the few urban investments that can cut time spent in traffic without major infrastructure works. For IT, telecom and road equipment companies, the project means contracts worth tens of millions of euros in the coming years, if the funding is confirmed.

    Unghiul Insider

    Bucharest has already lost the money for this same project once, because of appeals and delays. If the regional agency funding slips too, the city will have excellent feasibility studies and the same traffic lights it had in 2009. The pace of the tender will say more than any announcement.

    Surse

    Înapoi la prima pagină

    Contul meu

    Profil

    Teme urmărite

    Newslettere

    Alerte

    Urmărește companii și subiecte din pagina oricărui articol. Te anunțăm în cont când apare ceva nou despre ele.

    Alerte și ce urmărești

    Recomandări „Știrile tale”

    Folosim articolele pe care le deschizi și timpul petrecut pe ele ca să îți alegem știrile. Datele sunt doar ale tale.

    Vezi recomandările

    Articole salvate

      Confidențialitate

      Pentru descărcarea sau ștergerea datelor, scrie-ne la redactie@gotech.world.