Insider Daily, Smart City
Iași switches on, after more than ten years, the smart traffic lights it bought for 20 million euros
The first intersections activated are at Podu Roș. Next is Dimitrie Cantemir Boulevard, where the Traffic Management Centre reviews data before each switch-on.

Pe scurt
- The project started more than ten years ago and cost about 20 million euros at the time
- The Podu Roș lights were switched on in July 2026
- Next: three intersections on Dimitrie Cantemir Boulevard
Iași City Hall began in July 2026 to put into operation the smart traffic lights from a project started more than ten years ago, which cost about 20 million euros at the time. The first intersections activated were those at Podu Roș.
The start was not smooth. Jams appeared after activation, drivers needed time to adapt, and mismatches between signals were fixed by changing signal timings. City Hall said the situation had improved but was not yet ideal, and used the summer, with lighter traffic, for adjustments before the start of the school and university year.
The next stage covers Dimitrie Cantemir Boulevard, at its intersections with Regele Mihai I Boulevard, Șoseaua Națională and Aleea and Strada Decebal. There, the lights are not working or are only partly active. Activation depends on field measurements.
Cătălin Boghiu, director of the Digitalisation Department, said the city is already studying traffic data and that the lights must improve safety without disrupting traffic. The Traffic Management Centre has already changed timings at Baza 3 after complaints about trams heading towards Țesătura.
De ce contează
Iași paid for a system that sat unused for almost a decade. The fact that City Hall is now switching it on intersection by intersection, based on data, is a better model than a big-bang start, but it also shows the cost of equipment bought without an operating plan.
Unghiul Insider
Ten years between purchase and switch-on means some of the Podu Roș technology is already outdated. Traffic equipment has a useful life of 10-15 years. Iași risks starting to use the system just when it should be replacing it.