Romania wants to be the region's second-largest data centre market. Power will decide who wins
Projects totalling more than 1.8 GW are in the pipeline. Poland is accelerating, and investors mostly want fast grid connections.

Pe scurt
- Data centre projects announced in Romania in 2025 and 2026 exceed 1.8 GW.
- A 1 MW data centre costs around €7 to 8 million to build in Romania.
- Poland is set to grow from €3 billion in 2025 to €10 billion in 2030.
- Bucharest ranks 21st in the global Savills index of data centre potential.
Romania has data centre projects of more than 1.8 GW in the pipeline, according to figures presented in October at the Data Center Forum organised by Tema Energy. If they materialise, they would radically change the size of the local market.
The costs are considerable. In Romania, building a 1 MW data centre is estimated at €7 to 8 million. Today's main players are telecom operators and specialist providers, while newcomers include international developers and AI projects such as Runware's container factory and the Black Sea AI Gigafactory.
Regional competition is serious. Poland, the main destination in the area, is expected to grow from €3 billion invested in 2025 to €4.4 billion in 2026 and €10 billion in 2030. Bucharest ranks 21st in the Savills Power and Place Index, the global ranking of cities with the greatest potential.
Industry participants all say the same thing: the deciding factor is no longer land or price, but fast access to power. Some developers say that with an energy campus they could build facilities of hundreds of MW in about two years.
De ce contează
Data centres are the infrastructure that cloud and AI run on. A large local market means lower latency, data kept in the country and well-paid jobs in construction, energy and operations.
Unghiul Insider
Romania has real arguments: nuclear and hydro power, good connectivity and lower costs than the West. But it also has a track record of projects announced and never built. Grid connection times will make the difference. If an investor waits three years for a permit, they go to Poland. We propose that data centres be explicitly treated as projects of strategic interest, with guaranteed deadlines.